Fasteners Now 06-07-06 12:48pm

Cost and Time Estimation

Cost Estimate # 15
Product Code MS51981-40
Product Description 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
Quantity to Make 10,000 EA
Estimated Replacement Cost 0.0280 EA
Estimated Replacement Extension 279.65
Starting Date 06-07-06
Estimated Ship Date 07-18-06
Raw Material and Process
Raw Material Available Needed UOM Unit Cost per Total %
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
(Consumed in Step #2 - 60 Inspection)
8,790 10,000 EA   EA    
  Step # 1 - SCREW Screw Machine - Setup Cost
  4.00 Hours 15.00 Hour 60.00 21.46
  Step # 1 - SCREW Screw Machine - Machine Cost
  6.11 Hours 10.00 Hour 61.10 21.85
  Step # 4 - 60 Inspection - Labor Cost
  4.00 Hours 20.00 Hour 80.00 28.61
  41L40-.1625 - .162 - .163 41L40 Alloy 12' Rd Bars per Cam-Tech Spec CT41L40. 105,000 PSI Max. Original Mill Cert Required.
(Consumed in Step #1 - SCREW Screw Machine)
6,648.34 23.92 LB 164.44 CTW 39.33 14.06
  /CY - Cad Plate Type II Class 2 QQ-P-416 Rev. B. Baking to start within 4 hours after plating for a minimum of 23 hour at 375 +/-25. Cert. Req'd
(Consumed in Step #3 - 50 Plating)
Expense 23.92 LB 2.6836 LB 64.19 22.95
  /HEATTREAT41L40 - Heat Treat Steel 41L40 to Rc 46-53
(Consumed in Step #2 - 30 Heat Treating)
Expense 23.92 LB 2.2990 LB 54.99 19.66
Gantt Chart
Activity
06-15-06
06-23-06
07-02-06
07-10-06
|   |   |   |
PROCESS SETUP LEAD TIME
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
     
Ending: Fr 06-09-06 08:48am
PROCESS SETUP
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
   
Ending: Fr 06-09-06 12:48pm
PROCESS RUN
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
     
Ending: Mo 06-12-06 10:55am
WAIT FOR SHIPPING
Rochester Steel Treating Works, Inc.
/HEATTREAT41L40 - Heat Treat Steel 41L40 to Rc 46-53
   
Ending: Mo 06-12-06 3:00pm
OUTSIDE PROCESS
Rochester Steel Treating Works, Inc.
/HEATTREAT41L40 - Heat Treat Steel 41L40 to Rc 46-53
     
Ending: Mo 06-26-06 3:00pm
PROCESS SETUP WAIT TIME
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
     
Ending: Mo 06-26-06 9:00pm
WAIT FOR SHIPPING
Keystone Corporation
/CY - Cad Plate Type II Class 2 QQ-P-416 Rev. B. Baking to start within 4 hours after plating for a minimum of 23 hour at 375 +/-25. Cert. Req'd
     
Ending: Tu 06-27-06 3:00pm
OUTSIDE PROCESS
Keystone Corporation
/CY - Cad Plate Type II Class 2 QQ-P-416 Rev. B. Baking to start within 4 hours after plating for a minimum of 23 hour at 375 +/-25. Cert. Req'd
     
Ending: Mo 07-17-06 3:00pm
PROCESS LABOR TIME
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
     
Ending: Tu 07-18-06 11:00am
WAIT FOR SHIPPING
MS51981-40 - 10-24 x 1/2 Alloy Steel, Hex Socket, Oval Point, Cad Yellow Plated Set Screw per MS51981 Rev C and AN565F10H8 Rev 7
   
Ending: Tu 07-18-06 3:00pm